Pinecrest's ranch homes from the 1950s and 1960s sit on lots of about an acre, and the village asks a lot of a demolition application: two sealed surveys, tree surveys, an FPL electrical clearance, a Health Department septic abandonment, a village sewer-cap permit, and a letter confirming Freon recovery.

The village incorporated in 1996. Parrot Jungle's original 1936 site is now Pinecrest Gardens, which the village bought in 2002. On lots this size, trees are part of the job, and county rules treat a tree destroyed by root damage the same as one cut down, so equipment routes are set from the tree survey.

The procedures require DERM asbestos clearance, and only licensed contractors may apply. We arrange a licensed asbestos survey, coordinate the licensed abatement firm, the refrigerant recovery, the FPL clearance and the septic and sewer work, then file the application as the contractor of record.

A ranch house on an acre is rarely just the house. Pools, slabs, driveways, outbuildings and a septic system often come out together, and each is listed in the scope before the quote is set.

Sources: Wikipedia: Pinecrest, Florida · Miami-Dade County: tree removal permits

Who issues the permit in Pinecrest

Village of Pinecrest Building and Planning

Procedures require two sealed surveys, tree surveys, FPL clearance, septic abandonment, a sewer-cap permit, a Freon recovery letter and DERM asbestos clearance. Only licensed contractors may apply. Confirm with the village.

See the official page

This is general information, not legal advice. If you hire Romco, we apply for the permit as contractor of record. Miami-Dade demolition permit guide

What we quote in Pinecrest

Other work we quote

From first call to final

The order a Miami-Dade job follows

Romco Builders is a licensed Florida general contractor, headquartered in Fort Lauderdale. A garden shed and a mid-rise run through the same steps.

  1. Call or send the request

    Give us the address, photos or plans if you have them, and a plain account of what goes and what remains.

  2. Site visit

    We check how the building is framed, where the services enter, how trucks and machines get in, and what stands on either side.

  3. Scope and quote in writing

    You get a written scope listing removals, protections and haul-off, with any item that hangs on the asbestos survey called out.

  4. Survey, notice and permit

    A licensed asbestos survey, the DERM notice where it applies, the utility disconnects, then the permit from the city or the county.

  5. Take-down and hauling

    Work runs in the agreed sequence. Loads go to permitted facilities, and we keep the tickets.

  6. Final and closeout

    The inspector signs off the permit. You are left with a clean lot, or the shell you asked us to keep.

Questions

Demolition in Pinecrest

Can a Pinecrest homeowner pull the demolition permit without a contractor?

No. The village's demolition procedures say only licensed contractors may apply. Romco is a licensed Florida general contractor and files as the contractor of record. Confirm the current procedures with Building and Planning.

How much will my demolition cost?

We quote each job after seeing it, in person or through photos and plans when they show enough. The figure moves with the construction type, the floor area and height, the asbestos survey result, the utilities to be cut off, how machines reach the work, what stands next door, what must be kept, and how far the loads travel. A 1950s concrete block house and a 1990s frame addition can sit on the same street and quote very differently, which is why we publish no rates.

Why does Miami-Dade want an asbestos survey even for a house?

The county's own demolition requirements call for an asbestos survey on every demolition project, which is stricter than the federal rule for some small homes. A notice of demolition also goes to DERM, the county's environmental resources office, no later than ten working days ahead of the start date. The building permit is a different document and cannot stand in for it. We arrange a licensed survey, and a licensed abatement firm removes anything the work would disturb. Romco coordinates both and is not an abatement contractor.

How long does it take to get from first call to a cleared site?

We will not guess before the facts are known. The answer depends on the plan review queue at your city or the county, how fast the utilities issue their disconnect letters, what the survey turns up and the notice period that follows, any historic or condo board approval, and how big the building is and what it is built from. When we know those, you get a sequence that names what each step waits on.

Other Miami-Dade cities: Miami · Miami Beach · Hialeah · Coral Gables · Doral · Homestead · Miami Gardens · North Miami · North Miami Beach · Aventura · Sunny Isles Beach · Surfside · Bal Harbour · Key Biscayne · Palmetto Bay · Cutler Bay · South Miami · Miami Lakes · Miami Springs · Florida City · Sweetwater · Kendall

Every type, every size, all of Miami-Dade

Tell us what is coming down. We will put a quote on it.

Romco Builders is a licensed Florida general contractor, headquartered in Fort Lauderdale. A single interior partition or a complete building gets the same thing: a written scope and a quote.

Call (305) 760-9827Request a quote